Knowledge Base › Electrical Knowledge Base › How should the power-up sequence be set, and what if the inrush current is too high?
HomeModels
Table of contents

On this page

PLC & Programming (100 articles)

Quick Reference

  • PLC & Programming
  • Electrical & Electronic Basics (monthly)(每月更新中)
  • Electrical Control & Drawings (monthly)(每月更新中)
  • Drives & Actuators (monthly)(每月更新中)
  • Sensors & Detection (monthly)(每月更新中)
  • Industrial Communication & Networks (monthly)(每月更新中)
  • HMI & Host Systems (monthly)(每月更新中)
  • Industrial Robots & Motion Control (monthly)(每月更新中)
  • Mechatronic System Integration (monthly)(每月更新中)
  • Fault Diagnosis & Standards (monthly)(每月更新中)

How should the power-up sequence be set, and what if the inrush current is too high?

The power-up sequence decides whether the machine reaches a normal running state in one go, and the inrush current decides whether the switching supply and the breaker trip the instant you close the switch. Get the sequence wrong and the usual result is a supply protection trip and a PLC that keeps restarting; leave inrush alone and a bigger supply only postpones the problem. The sections below cover the order, where the current comes from, and how to tame it.

1. Why the power-up sequence decides whether the machine starts cleanly

A system contains low-voltage control supplies, a high-voltage main circuit and devices that need a communication handshake. If the main circuit is energised first and the control supply arrives afterwards, actuators can move before the controller is ready. If individual devices come up before the controller, the communication handshake may never complete. The rule is to establish control and communication first and bring in the power afterwards, so that the state of the machine is predictable at every moment.

2. A typical power-up sequence

The usual order runs like this. Energise the control circuit supply first and let the PLC complete self-test and reach RUN. Then supply the sensors and communication devices and confirm the stations are online. Then energise the control supply of the drives, the VFDs and servo drives, so they come to standby. Finally close the main circuit and let the motors and loads take power. Shutdown is roughly the reverse: drop the main circuit first, wait until the mechanism has stopped, then remove drive and sensor supplies, and take the control supply last. A delay relay or the PLC's own power-up delay will enforce the order automatically.

3. Where inrush current comes from

Inrush has three main sources. The first is the magnetising surge when a switching supply or transformer is energised, where a saturated core briefly draws several to a dozen times rated current. The second is charging a large DC-link capacitance, which momentarily looks almost like a short circuit. The third is surge currents adding up when several devices are energised at the same instant. Where a supply has power factor correction, its start-up behaviour can concentrate the surge further. The surge lasts only briefly, but long enough to trip an upstream breaker or blow a fuse.

4. Common ways to tame inrush current

Several measures are common. An NTC thermistor limits the closing current when cold, then drops in resistance as it warms. A limiting resistor with a bypass relay limits at start-up and is bypassed once settled. A switching supply with soft start or current limiting can be specified instead. Staggered power-up uses sequencing delays to separate the surges. A reactor can be added where needed. Each has a cost: resistors and thermistors introduce a voltage drop, a soft-start supply costs more, and staggering calls for extra timing control.

5. Shutdown and power-down sequence

Powering down is not simply the start-up order reversed. Two things matter. Any mechanism with a braking or holding requirement must be brought to a stop by the servo before the power is removed, otherwise it can run away. A controller that needs data retained should not lose its control supply until the shutdown write has finished. After a brief loss and restore of supply, for instance a voltage dip, confirm that the automatic restart strategy meets the safety requirement rather than assuming the machine will simply carry on.

6. Sequence, and the measures that go with it

StagePower-up orderPower-down orderMain measure
Control circuit supplyClosed firstOpened lastDedicated supply with filtering
PLC CPUSelf-test to RUN after control supplyCut only after data is writtenSet power-up delay and start mode
Sensors and 24 VApplied once the PLC is in RUNRemoved after the mechanism stopsTotal the 24 V current
Communication devicesWith the sensors, confirm onlineSame order as the control supplyOnline scan after power-up
VFD control supplyTo standby before closing the main circuitMain circuit first, then controlNo direct closing under load
Servo driveCheck home and limits before enablingStop first, then remove powerNever remove power while enabled
Main circuit powerClosed lastOpened firstBreaker with instantaneous trip margin
Supply inrushSurge peaks at closingDischarge takes timeLimiting, soft start or staggering
DC-link chargingTransient charge, near short circuitNeeds a discharge pathLimiting resistor with bypass relay
Restart after a voltage dipDecide recovery per strategyConfirm mechanism position is safeNo unconditional auto-restart

7. Notes

The practical way to fix the sequence is to draw a power-up timing chart first, marking the instant each stage is energised, what it depends on and the delay involved, and then select breaker and supply ratings from that chart. Inrush must be estimated at the least favourable instant, that is, with every device possibly energised at once, rather than selected from steady-state current. Where space and cost allow, the simplest arrangement is to feed the control supply and the power circuit from two separate switches, and let the control side's timing enforce the order.

8. References

General rules for low-voltage switchgear and controlgear follow GB 14048.1 (IEC 60947-1). Electrical installation, protection and earthing of the assembled equipment follow GB 5226.1 and IEC 60204-1. Requirements for adjustable-speed electrical drive systems follow the GB/T 12668 series. Breaker trip characteristics and supply inrush figures are as stated in the device manuals; the items listed here illustrate the accounting method.

9. Points to watch

⚠️ Three common traps:
(1) Selecting the breaker from steady-state current and ignoring closing inrush, so it trips on every power-up and the breaker gets blamed instead;
(2) Leaving a limiting resistor permanently in the circuit with no bypass, so it heats continuously and drops so much voltage the load cannot run;
(3) Letting the machine restart unconditionally after a voltage dip, so the mechanism moves with nobody confirming it is safe, risking damage or injury.

Before closing or opening the supply, confirm that no one is working on the machine and that guards are back in place. Live measurement should be carried out by competent persons using suitable insulation protection.