AutoShop's simulator runs your program logic without hardware: breakpoints, monitoring, forcing and sequence verification all happen on the PC. Used well, it halves field commissioning — low-grade logic errors (deadlocked flows, uncleared flags, missing interlocks) should never travel to the site. The sections below cover starting the simulator, verification method, what it can and cannot test, and the closing actions.
① Compile to zero errors (clear every error first; warnings at your discretion); ② pick "Simulation" from the tools/debug menu — the software raises a virtual PLC environment and offers to connect; ③ enter online mode as with a real machine: download to the simulator, RUN, open monitoring. From here the operations mirror the real machine: contact colours, device values, forcing and edits all work.
| Step | Action | Pit |
|---|---|---|
| 1 | Compile errors to zero | Simulating with errors — it will not start and the software gets blamed |
| 2 | Start the simulator | Do not mix simulator and real-machine connection modes |
| 3 | Download and RUN | Tick the download scope as on a real machine |
The simulator has no real inputs, so you play the field to verify logic: ① force inputs one by one following the process sequence (pressing start = forcing the start X ON for one edge); ② pair a watch table with forcing to mimic sensor arrival order; ③ walk the whole flow: power-up initialisation → every manual action → full automatic → alarm triggered → reset recovery, checking outputs at each step against the design; ④ boundary cases are mandatory: E-stop (force the E-stop input), power restoration (restart the simulator), mode switch (to manual while "running").
Verification technique: keep the design document's flow diagram beside you, walk the simulation along it step by step, tick each step on the diagram — simulation is "commissioning on paper"; an unticked flow reveals a hole in the logic.
| Can verify | Cannot verify | Countermeasure |
|---|---|---|
| Flow, interlocks, flag management | True timing (scan vs real response) | Leave real-machine time for critical timing |
| Alarm logic, state-machine flow | High-speed counting, interrupt real-time behaviour | Dedicated real-machine tests |
| Recipe switching, data handling | Real analog accuracy, comms real-time behaviour | Calibration and comms tuned on site |
| HMI linkage (panels against the simulator) | Driven loads, mechanical interference | Unloaded flow test on site |
Keep this table in mind and you will not misread "simulation passed, field failed" — simulation passing means the logic is right; the field still owes timing and physics. Con versely, logic that fails simulation has no business on a machine.
① Write a "verification list" before simulating: 10~20 conditions including boundaries, ticked one by one — otherwise simulation degrades into random clicking; ② fix and re-simulate on the spot when a problem appears, then re-run the whole list — fixing A and breaking B is the norm; ③ screenshot or record key flows — at delivery, this is the evidence chain that "the logic was verified".
| Symptom | Cause | Fix |
|---|---|---|
| Simulator will not start | Compile errors / component not installed | Clear errors, install the simulation component |
| Forced input has no effect | Forced at a scan boundary / wrong device | Monitor the device value before forcing |
| Timing differs from the real machine | Simulator time-base depends on load | Verify timing on the real machine |
| Simulation OK, field wrong | Timing, hardware or noise issues | Work the "cannot verify" list on site |
Simulation is the "logic examiner": flow, interlocks, states, data — anything reasonable on paper, it can examine. It is not the "physics examiner": timing, accuracy, noise, mechanics — those belong to the field. Clear the logic questions in simulation and field commissioning reduces to physics — that is simulation's real contribution to the schedule.
Simulation follows the Inovance AutoShop User's Manual simulation chapter; simulator-versus-real-machine behaviour notes appear in the same manual; commissioning safety (simulation cannot replace on-site safety verification) follows GB 5226.1 / IEC 60204-1 — the E-stop and safety loops are verified on the real machine.
Delivery iron law: a simulation verification record and a real-machine safety-loop verification record — both must exist.