Every stage added to a signal chain stacks its own error, and isolation accuracy plus temperature drift are the two report cards of a conditioning module. Understanding both, and how they compound, is the whole budget exercise.
Isolation accuracy is the deviation of the output from the ideal conversion, mainstream parts at plus or minus 0.1 to 0.2 percent of span, premium parts at 0.05. The system view matters: a 0.2 percent transmitter, a 0.2 percent isolator and a 0.1 percent AI input add linearly to 0.5 percent, while root sum squares gives about 0.3, with reality landing near the RSS but acceptance computed conservatively as the linear sum. Longer chains cost accuracy, which is exactly why 4-20 mA goes straight into the AI channel whenever isolation is not required, and why design files should carry a per stage accuracy budget on precision loops.
Temperature drift is the main source of error across the year: typical plus or minus 0.01 to 0.05 percent per degree C, so a 10 degree swing moves readings 0.1 to 0.5 percent of span, and the -10 to 50 range accumulates 0.3 to 1 percent. Conditioned cabinets suffer little, but outdoor and converter cabinets with wide swings feel it fully. Test by measuring a baseline at stable temperature, then warming the cabinet air gently and watching direction and magnitude, distrusting any module beyond plus or minus 0.05 per 10 degrees on critical loops. Treat drift as equal to accuracy in selection, and exclude datasheets that quote accuracy but stay silent on drift, since silence means they dare not print it.
Build the budget by listing accuracy and drift per stage, summing the worst case across the temperature range, and comparing with the process allowance. A 1 percent total requirement fails at 0.2 plus 0.4 of transmitter drift, plus 0.2 plus 0.3 of isolator drift, plus 0.1 for the AI, so the cure is a low drift isolator or fewer stages. The trade principle: accuracy just good enough, drift minimised first, because drift is a yearly error while accuracy is a one off offset, and paying 30 percent more to halve drift pays off in outdoor and wide swing cabinets. Accept with two point testing, ambient and warmed, both passing before the chain ships.
| Stage | Typical accuracy | Typical drift |
|---|---|---|
| Field transmitter | ±0.2% FS | ±0.02%/C |
| Isolating module | ±0.1~0.2% FS | ±0.01~0.05%/C |
| AI input module | ±0.1% FS | ±0.01%/C |
| Compensation cable | Around ±0.2% | Follows junction temperature |
| Full range total | Linear sum for acceptance | 0.3~1% over -10~50 C |
| Process allowance | Per design requirement | Trim stages or parts when exceeded |
Use this table for signal chain error budgets and conditioning module selection. List accuracy and drift per stage, sum the worst case over the temperature range against the process allowance, and cut stages or specify low drift parts when the budget breaks. Accept on ambient plus warmed two point tests, and drop any module whose datasheet omits drift, because drift is the error that never sleeps.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Performance and EMC per GB/T 18268 (IEC 61326); electrical safety per GB/T 5226.1 and IEC 60204-1. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.