On this page

Fault Diagnosis & Standards (100 articles)

Quick Reference

  • PLC & Programming
  • Electrical & Electronic Basics (monthly)(每月更新中)
  • Electrical Control & Drawings (monthly)(每月更新中)
  • Drives & Actuators (monthly)(每月更新中)
  • Sensors & Detection (monthly)(每月更新中)
  • Industrial Communication & Networks (monthly)(每月更新中)
  • HMI & Host Systems (monthly)(每月更新中)
  • Industrial Robots & Motion Control (monthly)(每月更新中)
  • Mechatronic System Integration (monthly)(每月更新中)
  • Fault Diagnosis & Standards (monthly)(每月更新中)

Detecting and fixing motor earth faults

An earth-fault alarm on a motor calls for a method: confirm with a megger, split the circuit to find the point, then decide between drying a wet winding and rewinding a punctured one.

1. How it works

Earth fault means insulation between winding and frame has failed. Working criteria at 500V megger: above 1 megohm hot and 0.5 megohm cold as the floor. A reading near zero is a metallic fault; tens or hundreds of kilo-ohms usually means moisture. Disconnect the drive or soft starter before testing and discharge the winding to frame afterwards - the megger stores charge and its 500V output kills electronics.

2. Practice and pitfalls

Localise by splitting: open the terminal box and separate the cable from the windings. Low resistance on the cable means a damaged run and a remade joint; low on the motor means test each phase at the terminal board to isolate the faulty one. Wet insulation in the tens of kilo-ohms that climbs as it dries is baked at 80~100C for 4~8 hours and retested every two hours until stable above 2 megohms. A punctured winding that stays near zero cannot be fixed on site - rewind or replace. Then close the loop on the cause: rubbing leads, worn slot wedges, a stator-rotor rub, or voltage spikes reflected from long unshielded cable on a drive.

3. Earth fault test and handling table

Megger reading at 500VVerdictRouteNote
Above 2 megohms, stableHealthyRun normallyLog the value
0.5~2 megohmsDamp or ageingDry out, retestCheck humidity and water
Tens of kilo-ohms, climbs when driedMostly moistureBake 80~100C for 4~8hRetest every 2 hours
Near zero, metallicPunctureRewind or replaceFind rub or worn wedges first
Cable side lowDamaged cableLocate and remake jointReview cable protection

4. Notes

The sequence: separate, split, dry first, condemn last. A recovered motor goes back only after the root cause is fixed and the new insulation value is on file.

5. References

The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Insulation requirements per GB/T 755 and handover test standard GB 50150, earthing and protection per GB/T 5226.1 clause 8. Always check the device datasheet and the product design file for ratings and derating.

6. Cautions

⚠️ Three common pitfalls:
① Meggering through a connected drive: the 500V output destroys IGBTs and boards - disconnect first
② Touching the winding right after testing: stored capacitive charge shocks - discharge to frame for a minute
③ Baking a punctured winding back into service: carbonised insulation never recovers, expect a phase fault

Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.