An electrical hazard survey is more than a walk-around: loose terminals, dead e-stops and overloaded ducts are all hiding hazards. This page gives an area-by-area checklist with acceptance criteria so nothing gets skipped.
Twelve checks inside cabinets: terminal tightness with infrared spot checks (anything over 20 K rise gets opened up), conductor insulation (tacky, chafed or cracked sleeving), wiring practice (one to two conductors per terminal, crimps seated, shields bonded per rule), clearance around heat sources (resistor banks with nothing stacked above), labelling (circuit numbers, terminal marks, warning tags), protection (live parts at IP2X or better, barriers intact), earthing (PE bar terminations and door straps), foreign objects (no drawings, rags or tools left inside), filters (clean and intact), condensation (heaters working, no water traces), spare fuses (sizes marked) and drawings (matching the machine).
Ten checks in the field: mobile cables in drag chains and reels for wear, exposed cores and illegal mid-span joints; temporary wiring — the worst offender — removed when its approval expires; industrial socket-outlets with correct IP and mechanical interlock, never domestic types on power; limit switches and e-stops function-tested twice yearly with unobstructed reach along the whole line; PE bonds on motors and frames, re-terminated when rusted or loose; guards and interlock switches functional; maintenance sockets with RCD trip tests; the environment (standing water, dust, corrosive media attacking equipment); 0.8 m of clear working space in front of distribution boards; and fire response (dry-powder or CO2 extinguishers in place, never water-based beside electrical gear).
Test-based surveys on fixed intervals: earth resistance yearly at 4 ohms or less; RCDs tested monthly by button and quarterly by measured current and time against 30 mA and 0.1 s; insulation sampling yearly on key circuits; infrared surveys twice yearly on busbars, terminals and breaker contacts with anything over 20 K tagged for action; and protection relay settings verified annually. Grade every finding: class A hazards (immediate shock or fire risk, such as broken PE or exposed live parts) stop the machine now; class B (serious but not immediate) get 24-72 hours; class C (documentation and housekeeping) get a week. Checklists close only with photos, owners, deadlines and sign-off — the record is also your evidence chain.
| Area | Focus | Criterion | Interval |
|---|---|---|---|
| Cabinet terminals | Tightness and temperature | Rise ≤20 K | Infrared twice yearly |
| Cabinet earthing | PE bonds and door straps | Voltage-drop method in spec | Twice yearly |
| Mobile cables | Wear and exposed cores | No bare copper, no joints | Monthly visual |
| Temporary wiring | Approval and expiry | No overdue, no rogue runs | Monthly |
| Emergency stops | Function test | Reachable, immediate stop | Twice yearly |
| RCD protection | Trip test | 30 mA and 0.1 s | Button monthly, measured quarterly |
| Board access | Working space | 0.8 m clear in front | Monthly |
| Infrared sweep | Joint temperature rise | Tag anything over 20 K | Twice yearly |
For monthly and quarterly plant electrical safety rounds and special campaigns. The checklist earns its keep only through execution and closure: tick with traces, photograph with numbers, rectify by deadline, recheck with signatures. Give inspectors the authority to stop on class A findings — the approval window is where accidents happen.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Machine electrical safety per GB/T 5226.1 (IEC 60204-1); LV distribution design per GB 50054; electrical safety practice per GB/T 13869. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.