Whether lightning, protective and functional earths should share one grid or stay separate has been argued for decades — and the answer is clear. This page covers the mechanism of both schemes, the modern standard recommendation and field practice.
Separate grids (independent earth electrodes 20 m or more apart) were meant to keep lightning current out of equipment via the shared network. In practice, however, potential differences and capacitive coupling between two grids during a strike can reach tens of kilovolts and punch through equipment insulation — modern practice has shown separate earthing to be more dangerous in storms. Shared (combined) earthing joins lightning protection, PE and signal references at one point so the whole system rises together with no difference to break down. GB 50057 and IEC 62305 both mandate the shared approach, with the combined resistance set by the strictest requirement (lightning 10 ohms, protection 4 ohms, communications 1 ohm — so 1 ohm for the grid).
Implementation rests on three principles. Single-point collection: all earth trunks (down-conductors, PE, shield trunks, DC functional earth) meet at the main equipotential terminal board (MEB); local boards (LEB) in rooms connect to the MEB by dedicated trunks. Spacing: down-conductors keep 1 m from signal cables or use metal conduit; the grid meshes at 3-5 m, buried 0.6-0.8 m, with electrodes 1.5 m clear of foundations. Resistance: 1 ohm or less for the combined grid when communications are involved, measured by the three-pole fall-of-potential method, with treatment soils or parallel electrodes where soil resistivity is high. Downstream of the MEB each branch runs its own route — a tree with one root and independent branches.
When separation is still legitimate: systems of different ownership or separate buildings (each grid complete on its own); intrinsic-safety systems with vendor and certification requirements on the earth reference; and laboratory floating measurements, which are better served by isolation transformers and floating references than by simply splitting earths. Legacy twin grids are not maintained but combined: bond them together at the MEB with a 35 mm² or larger copper tie — and where the measured inter-grid difference exceeds 1 V, this conversion is mandatory, retested before each storm season.
| Situation | Recommendation | Resistance | Key measure |
|---|---|---|---|
| All systems in one building | Shared earthing | ≤1 ohm with comms | Single point at MEB |
| Plant plus separate substation | Shared earthing | ≤1 ohm | Connect the trunks |
| Lightning and protective earth | Shared, mandated | Strictest value | Per GB 50057 |
| Legacy twin grids | Combine them | ≤1 ohm | Equipotential tie at MEB |
| Separate ownership buildings | Separate acceptable | Each to its own spec | 20 m minimum spacing |
| IS system special needs | Per certification | Per vendor | Follow the certificate |
| Floating lab measurements | Isolation plus floating | Per measurement need | Isolation transformer |
| Before storm season | Re-test | Recorded values | Once a year |
For plant earthing design, retrofits and annual checks. The verdict is firm: within one building, share the grid and collect it at one point; separation survives only across independent ownership. A legacy twin grid is cured by an equipotential tie, which removes the lightning back-flash risk at its root.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Lightning protection per GB 50057 and IEC 62305; information rooms per GB/T 50462; machine equipment earthing per GB/T 5226.1 (IEC 60204-1). Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.