Acceptance that waves at the safety equipment exposes every hazard after commissioning. This page provides the acceptance checklist for interlocks, light curtains, e-stops, two-hand controls and guards, each with a test method and pass criterion.
Start with the documents: the risk assessment (EN ISO 12100) lists the protective measures the acceptance verifies item by item; the safety circuit drawings carry their PL ratings per GB/T 16855.1; the device list names every interlock, curtain, e-stop and two-hand station; the vendor documents state response times and reset behaviour. Mismatches — an interlock on the drawing but missing on the machine, a curtain claimed where only a fence exists — are the first roadblock: fix the paperwork before testing functions. Have ready: finger and hand test rods, a stopwatch or response-time tester, a multimeter and means to simulate whole-body approach.
Device-by-device tests. Interlocks: the stop must trigger at a 1 mm door gap, reset only from closed, and locking interlocks must not release before full standstill. Light curtains: beam-by-beam interruption, measured response time, distance re-check, and immunity to arc light and direct sun. E-stops: every button, measured stopping time, latching and reset, reachability along the whole line. Two-hand controls: at least 250 mm between buttons, a synchronism window of 0.5 s maximum between presses, and no start from a single hand. Guards and fences: tool-required removal, mesh and height matched to their safety distance. Reset must never auto-restart the machine; an explicit start command is required.
The acceptance runs in four passes: document check, static inspection (position, fixing, marking), functional tests as above, then fault injection — broken sensor wires, welded contacts, and behaviour while any bypass is active. Record item, standard, measured value, verdict and defect photo numbers. Missing or failed safety functions are non-conformities: rectify, retest, then sign — never accept with defects open. Hand over the device list and test records with the machine and fold them into the periodic test plan (interlocks and e-stops twice yearly, curtain response twice yearly, guards quarterly).
| Device | Test | Pass criterion | Interval |
|---|---|---|---|
| Door interlock | Trigger at 1 mm gap | Stops at crack opening | Acceptance plus half-yearly |
| Locking interlock | Locked until standstill | No release while moving | Acceptance |
| Light curtain | Beam test plus timing | All beams, values in spec | Acceptance plus half-yearly |
| E-stop buttons | Each pressed, timed | Stops and latches in time | Acceptance plus half-yearly |
| Two-hand control | Synchronism test | 250 mm spacing, ≤0.5 s skew | Acceptance |
| Guards and fences | Mesh, height, fixing | Match safety distance | Acceptance plus quarterly |
| Reset behaviour | Observe after reset | No auto-restart | Acceptance |
| Bypass check | Verify in bypass state | Key plus time monitoring | Acceptance |
For new-machine acceptance, post-overhaul handover and annual safety reviews. The discipline: documents match hardware, every item tested — no sampling shortcuts — and defects rectified and retested before signature. Hand records over with the machine and schedule the periodic tests.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Acceptance per GB/T 5226.1 (IEC 60204-1) chapter 18 and GB/T 15706; interlocks per GB/T 18831 and guards per GB/T 8196; distances per GB/T 19876 (EN ISO 13855). Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.