Where the PE bar goes, where shields land and how the enclosure is earthed decide whether the earthing system means anything. This page gives the standard practice: layout, terminations, conductor sizes and acceptance numbers.
Layout: fit a PE bar (protective earth) and a shield bar (functional earth) — combined in small cabinets, separate but tied at one point in large or noise-sensitive ones. Position the PE bar in the lower entry zone (where the trunk arrives) and the shield bar in the upper signal-entry zone, both as tinned copper, sized by total load (typically 30×3 mm up to 50×5 mm). An earth stud at the cabinet base (M8/M10), welded or clamped to the frame with paint removed and faces tinned, connects the enclosure through 16 mm² or larger green-yellow conductor to the plant earth trunk. Doors and removable panels need braided bonding straps of 6 mm² or more — painted hinges are not an earth path.
Termination and sizing: terminate each conductor at its own point; never stuff several into one terminal unless it is rated for it. Crimp with proper tools and pull-test samples; use serrated washers to bite through oxidation; torque M6 to 8 N·m, M8 to about 15 N·m, M10 to about 25 N·m; coat threaded joints with conductive paste. Conductor sizing per GB/T 5226.1: PE trunk at half the phase conductor and at least 6 mm² (cap 25 mm², above which PE equals phase cross-section); branch PE equals phase size up to 4 mm² and half of it from 4 to 25 mm²; shield pigtails 2.5 mm² or more onto the shield bar; the signal 0V reference runs separately and never shares a conductor with PE. Mark PE in green-yellow along its length and label the shield bar.
Acceptance and inspection: measure bonding continuity from any exposed conductive part to the earth stud by the voltage-drop method per GB/T 5226.1 (typically on the order of 0.1 ohm); test door straps with the door open; spot-check shield bonds with a micro-ohmmeter under 0.02 ohm; and verify the path to the plant trunk. Inspect twice yearly: sample 10 percent of joints for resistance, check braids for rust and breakage, re-torque samples. On retrofits, new equipment PE bonds to the PE bar — never to a nearby painted screw — and reassembled painted faces get re-treated.
| Item | Standard practice | Parameter | Forbidden |
|---|---|---|---|
| PE bar material | Tinned copper bar | 30×3 to 50×5 mm | Aluminium substitute |
| Cabinet earth stud | M8/M10 welded or clamped | Paint removed, tinned | Clamping on paint |
| Door bonding | Braid 6 mm² or larger | Checkable with door open | Relying on hinges |
| PE trunk | Half phase, ≥6 mm² | Cap 25 mm² | Series borrowing |
| Branch PE | Per GB/T 5226.1 table | Half phase from 4-25 mm² | Borrowed colours |
| Shield pigtails | 2.5 mm² or more | Onto shield bar | Sharing with PE |
| Termination torque | M6 8 N·m, M8 15 N·m | Serrated washers | Hand-tightening |
| Acceptance test | Voltage-drop PE resistance | Sample 10 percent of joints | Visual only |
For building and accepting earthing in LV assemblies, control and drive cabinets. Uniform practice is everything: one shop-wide standard for bar size, termination style and colour marking gives inspections a baseline. Door straps and painted faces are where problems cluster.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Cabinet bonding per GB/T 5226.1 (IEC 60204-1); LV assembly earthing per the GB/T 7251 series; EMC earthing per IEC 61800-3. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.