Repairs get the line running; real fixes cost downtime. A two-account decision framework, a registry that keeps temporary measures temporary, and how to slot permanent work into the production rhythm.
Compare two accounts. The downtime account: what one hour of this line costs, versus two hours of running repair against eight hours of proper cure. The recurrence account: how long the temporary measure will hold, what a repeat failure costs - unplanned stops run three to five times the cost of planned ones. If downtime is expensive and the interim measure is trustworthy for a week or more, repair now and schedule the cure; if the measure is shaky, or the equipment is a safety or bottleneck item, cure immediately.
Temporary measures live under discipline: register what was bypassed, what protection is lost, an expiry of two weeks maximum, and the exit condition - spare arrived or planned shutdown. The sheet hangs on the machine and is read at every shift handover. Two rules are absolute: safety devices are never bypassed by anyone, and expired items escalate automatically. For the cure itself, piggyback on existing planned stops, order spares before booking the window, and write the fallback plan - if the day runs out, production resumes. Acceptance is quantitative: fault counts, alarm logs and accuracy data, before versus after.
| Situation | Strategy | Reason | Note |
|---|---|---|---|
| Downtime costly, interim measure solid | Repair now, cure within a week | Minimise loss | Register the expiry |
| Interim measure unreliable | Cure immediately | Recurrence costs more | Confirm spares first |
| Safety function involved | Immediate cure, no bypass | Safety red line | No one may approve bypass |
| Bottleneck machine, repeat faults | Cure takes priority | Repeat losses multiply | Use fault data to argue |
| Spares not yet arrived | Keep running, chase order | Waiting idle costs more | Escalate when overdue |
Weigh both accounts, register every interim measure, never bypass safety, and piggyback cures onto planned stops. The time bought by the repair belongs to the cure, not to waiting for the next breakdown.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Machinery safety functions and the prohibition on defeating safeguards per GB/T 5226.1 (IEC 60204-1). Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.