The same machine runs fine on line A and fails constantly on line B: cross-line comparison digs out problems no single line can see. This page covers the comparison dimensions, how to build a baseline, and the path from difference to root cause.
Dimensions and data preparation. Four dimensions: failure rate — monthly fault counts, downtime and MTBF per machine type grouped by line; failure modes — the distribution of modes per line (drives failing from cooling on one line and from dust shorts on another points straight at the environment); spares consumption — consumption speed differences flag heavier duty or worse environments; and parameters plus environment — load rate, temperature, humidity, dust, shifts and process. Preparation demands: a unified equipment registry (verify model and batch, since hardware batches themselves shift failure rates), standardised fault coding (one plants loose terminal is another plants contact fault, and the comparison dissolves), and consistent time bases.
Baseline and analysis. Use the median failure rate across lines — never the mean, which outliers drag — as the baseline, and flag any line deviating more than 50 percent. Attribute differences in order: environment first (measure it — a line with triple drive failures proves 8 C hotter with lax filter cleaning); then process load (cycle times, load rates, start-stop frequency); then operation and maintenance (SOP adherence, grease and consumable brands); then installation history (later retrofits that squeezed cable routing and cooling). Every hypothesis needs data or a field measurement — no armchair attribution. A typical find: identical servos failing twice as often on the line running two continuous shifts with no cooling gaps, the root cause being accumulated bearing temperature rise.
Closing the loop. Actions follow the attribution: environment fixes get ventilation and filter regimes; load causes get schedule changes or upgraded equipment; maintenance gaps get unified SOPs pulled up to the best lines standard; installation causes get rework of routing and cooling. Track the effect: re-measure failure rates three months after each measure — regression toward the baseline is the pass criterion. Institutionalise: a monthly cross-line briefing (rankings, flagged machines, action tracking), a quarterly deep-dive on one or two machine types, and standardisation of the best lines practices — often the best improvement handbook lives next door. Mind the trap: only compare comparable equipment and duty, and scope conclusions accordingly.
| Dimension | Compared content | Abnormal criterion | Common root cause |
|---|---|---|---|
| Failure rate | Monthly faults and MTBF | Over 50 percent off median | Environment or load |
| Failure modes | Mode distribution | Marked share shift | Environmental signature |
| Spares consumption | Consumption speed | Outlier line | Heavy duty or poor environment |
| Environment | Temp, humidity, dust, vibration | Measured over 5 C difference | Ventilation and filter regime |
| Process load | Cycle and load rate | Runtime difference | Scheduling and product mix |
| Maintenance execution | SOP adherence, consumables | Execution and brand gaps | Inconsistent standards |
| Installation history | Retrofit records | Squeezed routing and cooling | Later-modification legacy |
| Shift pattern | Continuous running | No cooling gaps | Accumulated temperature rise |
For multi-line plants upgrading equipment management. The core: a median baseline, four comparison dimensions and a four-step attribution (environment, load, maintenance, installation), with a three-month retest closing each action. Standardising the best lines practice is the biggest dividend.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Management practice per GB/T 5226.1 (IEC 60204-1) and GB/T 33174 asset management; reliability metrics such as MTBF per the relevant reliability standards. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.