A repair without a review is a lesson half-learned - and the same fault returns within months. A fixed five-part structure, the five-whys chain, and prevention items that can be verified.
The report has five fixed sections: an overview with time, location, equipment, symptoms and impact including downtime; a timeline of the actual response, unvarnished; a cause analysis separating the direct cause from the root cause - a welded relay contact is direct, an undersized control transformer making the contactor chatter is the root; prevention measures matched to each root cause; and attachments - photos, waveforms, parameter logs. One to three pages, never five.
Dig with five whys until the answer lands in design, selection or procedure: the overload trips because current exceeds setting, because the load grew, because the belt was over-tensioned, because the worn installation datum was never checked, because no inspection item covers it - that last one is the root. Blaming a person is not a root cause; redesign the setup or the checklist instead. Prevention items must be executable and verifiable - extend the inspection interval to two weeks with a temperature check, name the owner and the date. Close with a monthly look back at old reviews: whether the fixes held is the real measure of the exercise.
| Section | Content | Hard requirement | Common flaw |
|---|---|---|---|
| Overview | Time, place, equipment, impact | Downtime stated | Reads like a confession |
| Response timeline | Who did what, when | Honest, unedited | Key steps skipped |
| Cause analysis | Direct and root causes apart | Five whys to procedure level | Stops at part swap |
| Prevention | One item per root cause | Executable, verifiable, owned | Vague watch more closely |
| Attachments | Photos, waveforms, logs | Corroborate the text | No evidence at all |
The value shows at the next fault: pull the old report and check whether the root cause really died. File by equipment number, reread one old review each month, and verify the measures still exist.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Fault finding principles per GB/T 5226.1 clause 18, records and quality management per GB/T 19001, switchgear documentation per GB/T 7251.1. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.