What counts as a real inspection — how often, what is abnormal, how to record — are the questions the floor asks most. This page answers the top ten in plain form, with frequencies, criteria and recording rules.
Frequency and scope. Pre-shift takes two minutes on displays, sounds and smells; daily rounds run weekly in normal shops and daily in dusty or wet ones; instrumented inspections (infrared, earth resistance) run monthly to quarterly. Inspection differs from a walk-through by standardisation and traceability: a checklist executed and recorded. Scope covers what is reachable in operation — appearance, temperature, sound, indicators — never opening covers, which belongs to planned maintenance. Night shifts run the pre-shift checks folded into the shift-handover record, raising work orders on the spot rather than waiting for the day crew.
Judgement and action. Motor housing: comfortable to the back of a hand for 3 seconds is about 60 C; 80 C is the limit for class B, and beyond that check load and cooling. Terminal discolouration signals heat — confirm with the pyrometer, tag anything over 20 K rise, de-energise on blackening. Small fixes within reach (snugging a visibly loose terminal) are fine; anything involving de-energising, opening covers or live measurement goes through a work order. A tired fan gets reported even though the machine runs fine: a replacement fan costs one percent of a burned drive, and fan decay precedes cooling failure.
Recording and management. A record that matters is handwritten on the spot, attaches photos and numbers for every anomaly, and feeds a monthly trend meeting. Keep the sheet to one page — anything longer gets filled carelessly — and grant inspectors written authority to stop on class-A findings without asking permission up the chain. The health check of the whole system is the order statistics: monthly work orders raised versus closed, with a closure rate under 90 percent meaning the process is idling — fix the process before adding checklist items.
| Question | Answer | Criterion | Note |
|---|---|---|---|
| How often | Pre-shift plus weekly plus monthly | Weekly, or daily in harsh areas | Scale with environment |
| Versus a walk-through | Standardised and traceable | Checklist executed | Walks leave no record |
| Motor housing temp | Hand test or pyrometer | ≤80 C (class B) | Check load and cooling |
| Terminal discolouration | Confirm by temperature | 20 K rise gets a tag | Black means de-energise |
| Repair authority | Snug tightness only | No live work, no covers | Everything else on order |
| Anomaly recording | Work order mandatory | Closure rate ≥90 percent | No verbal handoffs |
| Fan noise | Always report | Early-warning signal | Cheapest prevention |
| Sheet filling | On-site, handwritten, photos | One page | Monthly trend meeting |
For training programmes and newcomer induction. The Q&A format clears the grey zones: frequencies scale with environment, authority is explicit, recording has hard requirements, and the closure rate tells you monthly whether the system is real.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Maintenance per GB/T 5226.1 (IEC 60204-1); electrical safety per GB/T 13869; motor temperature and insulation bases per GB/T 755. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.