Uneven earth potential across the plant brings communication bit errors and analog drift. Equipotential bonding pulls all metalwork to the same potential and underpins communication stability. This page covers the principle, the construction practice and acceptance numbers.
Plant earth is never an ideal zero: lightning induction, large motor starting, VFD leakage and welding work all shift local potentials, normally by millivolts but by volts or tens of volts during events. When a communication cable bonds to different potentials at each end, that difference drives current through the shield or signal reference and straight into the signal. Equipotential bonding ties cabinets, trays, enclosures and earth bars into one low-impedance body so potential differences approach zero, removing the driving force behind ground loops. Many untraceable faults — intermittent bit errors, update-time jitter, slow analog drift — trace back to missing or degraded bonding.
Construction has three levels. Device level: each devices PE terminal and shield-earth terminal connect with at least 4 mm² green-yellow conductor to the local bonding continuous conductor or tray. System level: cabinets carry PE and shield bars (they may be combined), tray sections are bonded along the whole run with braided jumpers or galvanised connectors with paint removed, and the tray is earthed at both ends and every 20 to 30 m. Network level: communication shields bond 360 degrees at both ends to their local bonding points, with power and signal trays separated by 200 mm or a metal divider. Every joint must measure below 0.02 ohm with a micro-ohmmeter, protected with conductive paste and anti-corrosion paint; trunk conductors at least 16 mm², branches 4 to 6 mm².
Accept three numbers at handover: steady-state potential difference between any two bonding points under 1 V (transients aside), joint resistance below 0.02 ohm, and earth resistance of the combined grid at 4 ohm or less (1 ohm where the communication system demands). Maintain twice yearly: sample 10 percent of joints, check jumpers for rust and breakage, and re-earth any tray modified with new cutouts. Watch two common destroyers during retrofits: paint or insulating blocks turning joints into insulation, and plastic tray brackets breaking continuity. On communication faults, measure the earth potential difference first — over 0.5 V means fix earthing before touching anything else.
| Item | Requirement | Test method | Interval |
|---|---|---|---|
| Joint resistance | <0.02 ohm | Micro-ohmmeter sample | Twice yearly, 10 percent |
| Potential difference | <1 V steady state | Multimeter AC/DC | On every comms fault |
| Combined earth resistance | ≤4 ohm (≤1 ohm for comms) | Earth tester | Yearly |
| Trunk conductor | ≥16 mm² copper | Visual and records | At retrofit |
| Branch conductor | 4-6 mm² green-yellow | Visual | At retrofit |
| Tray jumpers | Braid or galvanised connector | Per-section visual plus sample | Twice yearly |
| Shield earthing | Double-ended 360-degree | Visual plus micro-ohmmeter | After any rework |
| Corrosion protection | Conductive paste plus paint | Visual | Yearly |
For plant earthing design and retrofit acceptance. Bonding is the invisible foundation of communication stability: degraded, it produces endless mysteries. Number and photograph joints on new builds, and make bonding restoration a mandatory acceptance item on retrofits.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Bonding requirements per GB/T 5226.1 (IEC 60204-1) and GB/T 16895 building installations; EMC practice per IEC 61800-3. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.