Acceptance insulation testing is not one quick megger sweep: which circuits, at what voltage, with what pass values and what records — GB/T 5226.1 defines it all. This page lays out the complete acceptance-level procedure.
Scope and voltage per GB/T 5226.1 section 18.3: power circuits (busbars, cables, motor windings) to PE, phase-to-phase with links opened, and control circuits to PE. Test voltages follow rated voltage: 250 V dc for control below 50 V, 500 V dc for 50-500 V, 1000 V dc above. Electronics — drives, PLCs, servo amplifiers — must be disconnected or bypassed first, since megger voltage destroys modules; this is the main difference from whole-machine testing. Surge protectors come out of circuit too, because their varistors drag readings down. In humidity above 90 percent or after wetting, dry the equipment before testing for stable results.
Pass criteria and procedure. The standard requires 1 megohm minimum at 500 V dc, but new power circuits typically read far higher — anything under 10 megohms deserves a moisture and contamination check. Sequence: de-energise, verify, discharge; disconnect electronics and SPDs; open any neutral-to-PE connection per the design; measure each circuit segment to PE and phase-to-phase for 60 seconds, reading the stable value; record temperature and humidity, since resistance roughly doubles for every 10 C drop. Afterwards discharge the tested circuits fully — long cable runs and windings hold charge — before restoring any connection.
Records and management: log equipment number, date, ambient conditions, instrument details, test voltage, each 60-second reading and the tester signature, then file with the equipment records and compare against factory values — a large drop suggests transport wetting. During operation, retest key circuits (motors, heaters) at annual maintenance and plot trends; a 50 percent year-on-year fall or an absolute value near 1 megohm schedules repair. The classic mistakes: meggering with electronics and SPDs still connected, using high voltage on control circuits and puncturing relay coils, and reconnecting before discharge.
| Circuit | Test voltage | Pass value | Notes |
|---|---|---|---|
| Control below 50 V | 250 V dc | ≥1 MΩ | Electronics disconnected |
| Power 50-500 V | 500 V dc | ≥1 MΩ | New circuits expected 100 MΩ plus |
| Above 500 V | 1000 V dc | ≥1 MΩ | Special provisions apply |
| Electronic circuits | Per maker | Maker criteria | Megger forbidden directly |
| SPD circuits | Disconnected for test | Visual after restore | Varistors depress readings |
| Motor windings | 500 V dc | ≥1 MΩ | Disconnect drive first |
| Heater circuits | 500 V dc | ≥1 MΩ | Test cold |
| Operational retests | 500 V dc | Trend comparison | Half-year fall of 50 percent means repair |
For factory acceptance, site acceptance and annual maintenance testing alike. Three key actions: disconnect electronics and SPDs before testing, measure each circuit for 60 seconds to a stable reading, and discharge afterwards. Trend the numbers in the archive — the slope tells more than any single pass value.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Testing per GB/T 5226.1 (IEC 60204-1) section 18.3; methods per IEC 60034-27 and GB/T 50150 hand-over test standard. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.