Night demand drops to a tenth of daytime and the main pump either crawls in its inefficient band or cycles constantly. This page compares the three pressure-holding strategies and gives the sleep-mode parameters and anti-cycling checks.
Between midnight and 5am demand often falls to 10~20 percent of daytime, so the main pump bottoms out at 25~30Hz while pressure still climbs, then the loop oscillates and the motor starts five or six times an hour. Small pressure tanks under 100 litres drain in minutes and restart the pump. The cures are staged: a jockey pump at 5~10 percent flow with a small tank for larger systems, a 300~1000 litre bladder tank holding 0.25~0.35MPa for tiny demands, or the drive built-in sleep function.
Sleep parameters: sleep threshold at 30~35Hz, sleep pressure 0.02~0.05MPa above target, sleep delay 120~300 seconds to ride through brief night use, wake pressure 0.02~0.03MPa below. If start-stop intervals stay under 5 minutes, the tank is too small or the thresholds are wrong. Measure the night leakage rate first by closing valves and watching the pressure decay; if leakage exceeds 30 percent of night demand, fix the leaks before tuning anything, otherwise every strategy works for the leak.
| Scheme | Scale | Key hardware | Starts per night | Cost |
|---|---|---|---|---|
| Jockey pump | Medium and large | Small pump plus tank | Under 2 | Moderate |
| Tank holding | Small | 300~1000L bladder tank | 2~4 | Low |
| Sleep mode | Universal | Drive sleep function | 1~3 | None, built in |
| Timed rotation | Medium | PLC timetable | 2~3 | Low |
| Night pressure trim | Tower systems | PLC target switch | Pump keeps running | None |
| Mains backup | Transitional retrofits | Contactor bypass | By pressure switch | Lowest |
Before choosing, measure the night leakage rate by pressure decay and the real tank volume. Log start-stop events for a week after tuning before freezing the parameters.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Water supply design per GB 50015, machine electrical safety per IEC 60204-1. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.