Both pulse trains and fieldbuses make servos move, but multi-axis interpolation, synchronisation accuracy and diagnostic efficiency are a generation apart. This page compares wiring, synchronisation, diagnostics and cost, and draws the line between pulse-adequate and bus-mandatory applications.
Pulse control sends position as a pulse count: the PLC emits, the servo travels. It is cheap and universal, any PLC with high-speed outputs will do, with the pulse rate ceiling, typically 200kHz to 4MHz, setting the product of top speed and resolution. Three drawbacks: the command is position open-loop only, speed and torque stay inside the servo and the PLC never sees actual position, so following error and lost steps are the servo private business; wiring runs 4~6 cores per axis, over 40 for eight axes; and there is no synchronisation mechanism, each axis starts and stops on its own pulses, which is one root cause of circular interpolation drawing ellipses.
Industrial buses compress the control cycle to 125 microseconds to 1ms with distributed-clock sync below one microsecond, a synchronisation pulse control cannot reach. The bus carries back actual position, torque, following error and alarm codes in full, so the controller watches every axis live and alarms arrive with an axis number and a description. One daisy-chained cable replaces dozens of cores and can pick up I/O on the way, and parameters, torque limits and absolute positions travel on the bus with no analogue or DI points. The price is a bus-master motion PLC or controller, some 20 to 30 percent more, and commissioning that requires bus configuration literacy: EDS or GSDML files, station addresses, sync periods.
Choose by need: single or two independent axes, moderate speeds, plus or minus 0.1mm point accuracy and tight budgets stay on pulses. Multi-axis interpolation, electronic cam and flying shear synchronisation, live torque monitoring for predictive maintenance and systems past 20 axes go bus. The grey zone of three to eight axes with moderate interpolation demands pays 20 to 30 percent more for bus but saves tuning pain; weigh it against product tolerance and machine life. Hybrid is common: critical axes on bus, auxiliaries on pulses, one controller with both outputs.
| Dimension | Pulse control | Bus control | Gap explained | Selection lean |
|---|---|---|---|---|
| Control cycle | 1~4ms, PLC scan | 125μs~1ms | Bus an order faster | High speed, bus |
| Axis synchronisation | None, axes independent | Below 1μs, distributed clocks | Root of interpolation accuracy | Interpolation, bus |
| Feedback data | Alarm contacts only | Position, torque, error in full | Diagnostic generation gap | Predictive maintenance, bus |
| Wiring, 8 axes | 40~50 cores | One daisy-chained cable | Ninety percent saved | Tight cabinets, bus |
| Controller cost | Standard PLC | Motion PLC or controller | 20~30 percent higher | Weigh by need |
| Commissioning skill | Low | Bus configuration literacy | Learning curve | By team capability |
One-line rule: interpolation and synchronisation demand a bus, independent single-axis motion does not. Retrofit note: bus systems need bus-type encoders, incremental pulse encoders do not plug into EtherCAT servos, so budget the encoders and cables too, and run topology and sync-quality checks before any tuning.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Real-time Ethernet per IEC 61784-2; equipment safety per GB/T 5226.1 / IEC 60204-1. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.