E41-462 · Other Selection · Compressor Foundation Cracking · ★★★★
After 6 months of operation, the compressor foundation developed cracks (about 1m long, 0.5mm wide) and the anchor bolts loosened. The foundation was cured for only 3 days after construction (standard ≥28 days).
The compressor foundation (C30 concrete, volume approx. 20 m³) was put into service only 3 days after pouring, instead of the standard 28-day curing. At 3 days the concrete reached only about 30% of its design strength (C30 × 0.3 = 9 MPa), far below the ≥70% (21 MPa) required before installation. Under the equipment self-weight (about 20 t) and operating vibration after installation, the foundation settled and deformed unevenly. Six months later cracks appeared (shrinkage plus stress cracks), about 0.5 mm wide. The anchor force of the foundation bolts was lost on the cracked base and the bolts loosened. On the loosened foundation the compressor developed additional vibration (rising from 5 mm/s to 15 mm/s), accelerating crack propagation.
① The equipment foundation must be cured ≥28 days (standard curing, covered with wet burlap and sprinkled with water).\n② Equipment may be installed only after the foundation strength reaches 70% of design (usually ≥14 days).\n③ Anchor-bolt grout must be cured ≥3 days before the bolts are tightened.\n④ Treat foundation cracks by injecting epoxy resin (deep cracks) or applying surface sealing (hairline cracks).\n⑤ Mass concrete foundations should have expansion joints and cooling water pipes (to control thermal-difference cracking).
FT_Machine Design Handbook