E41-955 · Chain Drive Selection · Double-Strand Chain Drive · ★★★

Problem Description

On a double-row chain drive the two chains were out of phase; the more heavily loaded one broke first and the other followed, and the chain came off.

Root Cause

First, the two chains must be of equal length and in phase; manufacturing and wear differences make the load uneven, with one chain carrying > 70%. Second, the offset-loaded chain breaks first and the other then breaks from the impact. Third, the chain came off. [Root cause] Out of synchronization.

Corrective Solution

① Double-row chains must be from the same maker and batch, of equal length and in phase
② Check that both chains have equal tension during assembly
③ Select an integral double-strand chain to reduce the difference
④ Replace both together at the same time
⑤ Forbid mixing batches
⑥ Verify equal load sharing
⑦ Check synchronization whenever a chain breaks

Checklist

Reference

FT_Belt & Chain Drive Design

Related model download:Understood the principle and ready to try?Go to MOULDL to download related 3D models and CAD drawings for free »
MOULDL · Mechanical Engineering Knowledge Base · free self-study reference for machine designers, 3D CAD models at MOULDL