E42-160 · Welding Deformation and Defects · Welded Slewing Frame 1600×1200 · ★★
After welding frame diagonal difference 6mm (allowable 2); flatness 0.05.
[Improper Sequence] Welded one side fully before the other; asymmetric shrinkage. [Distortion] Longitudinal shrinkage difference ΔL=4mm on two sides causes frame twist 3mm/m. [Design Omission] No symmetric skip-welding sequence specified; no pre-set reverse deformation; straightening adds 4h/piece.
1. Develop symmetric segmented skip-welding sequence drawing.
2. Long welds welded back-step from center outward.
3. Add 3mm reverse deformation before welding.
4. Rigidly clamp with fixtures to prevent twist.
5. Control interpass temperature ≤150℃.
6. Relax 24h after welding before straightening.
7. Mechanically level when diagonal difference exceeds 2mm.
8. First-piece full CMM inspection each batch.
GB 50661-2011