E46-101 · Assembly Sequence & Datum · Welded Housing · ★★
The shaft assembly was installed in the housing and the cover closed, and the bracket was then welded on the outside; after welding the main shaft bore of the housing shifted 0.8mm relative to the locating datum and the end cover could not be fitted.
[Mechanism] The welding was carried out after final assembly, and the weld shrinkage displaced the already-assembled datum bores.
[Calculation] The weld shrinkage of about 0.8mm exceeds the 0.2mm assembly coaxiality tolerance and the end cover spigot cannot be inserted.
[Design gap] The sequence of welding to final shape before assembly was not specified.
① Change the assembly sequence: weld the bracket and relieve stress first, then install the shaft assembly and end cover, so thermal distortion cannot damage the datum
② Leave allowance before welding: leave machining allowance on the welded structure and machine the datum faces as a whole after welding to ensure bore accuracy
③ Age after welding: arrange aging or annealing after welding to remove residual stress and stabilize the dimensions
④ Re-measure the datum: before assembly re-measure the housing bores and datum faces and confirm the offset is within tolerance
⑤ Fixture location: use an assembly fixture to fix the relative position of the housing and bracket and reduce human error
⑥ In-process inspection: check the datum bores after welding to detect offset early
⑦ Quality verification: confirm by CMM measurement that the bore positions relative to the datum meet the drawing
⑧ Standardize process: write weld-before-assembly into the assembly process card, controlling at the source
JB/T 5000.10-2007 General technical conditions for heavy machinery - Part 10: Assembly