E46-122 · Assembly Sequence & Datum · Welded Tube Sheet · ★★
The tube sheet holes were finish-machined before the tubes were welded on, and no machining followed the welding; the hole positions shifted by 1.5mm and the tubes could not be inserted.
[Mechanism] Finish machining was done before welding and no machining followed, so the welding distortion moved the already-machined holes.
[Calculation] Welding shrinkage shifted the holes by 1.5mm, exceeding the 0.3mm fitting tolerance.
[Design gap] Weld-before-machining was not specified.
① Weld before machining: complete the tube welding and stress relief first, then machine all the tube sheet holes
② Leave stock for welding: leave machining allowance at the welded areas and finish-machine to size after welding
③ Control distortion: weld symmetrically in segments to reduce distortion
④ Relieve stress: anneal after welding to stabilize the dimensions before machining
⑤ Re-measure hole positions: after machining measure the hole positions to confirm they are ≤ the tolerance
⑥ In-process inspection: check for distortion after welding to detect problems early
⑦ Quality verification: trial-fit the tubes to confirm there is no interference
⑧ Standardize process: write weld-before-machining into the process, controlling at the source
GB/T 19866-2005 Welding procedure specification