E46-129 · Assembly Sequence & Datum · Machine Final Assembly · ★★★
Only after the whole machine was finally assembled was it found that the hydraulic power unit turned the wrong way and the sensor zero was off, so the assembly had to be stripped down for rework and the schedule slipped.
[Mechanism] Components were not tested and accepted before final assembly, so defects were carried into final assembly where they are hard to trace.
[Calculation] The troubleshooting effort after final assembly is several times higher than component testing.
[Design gap] No component testing operation was defined.
① Test components first: test each component such as the hydraulic power unit, electrical control and drive individually before final assembly
② Issue reports: produce records and acceptance reports from component testing as the prerequisite for final assembly
③ Confirm interfaces: before final assembly confirm the interfaces between components, such as oil ports and electrical matching
④ Staged final assembly: carry out final assembly layer by layer, checking continuity and function at each layer
⑤ Prevent wrong installation: check component numbers against the test records to prevent mismatching
⑥ In-process inspection: re-test after each assembly layer to detect abnormalities early
⑦ Quality verification: confirm all components work together correctly by a trial run of the whole machine
⑧ Standardize process: write the component testing operation into the assembly process, controlling at the source
JB/T 5000.10-2007 General technical conditions for heavy machinery - Assembly