E46-168 · Fastening & Anti-Loosening · Newly installed unit · ★★
No re-tightening was scheduled during the initial operation of a new unit; after running-in under load the preload of the anchor and flange bolts decayed by about 20%, some joints loosened slightly, and vibration increased.
[Mechanism] After the initial load the micro-asperities of a new joint face are flattened, the bolt elongation decreases, and the preload drops.
[Calculation] Running-in settles the joint face, and the preload decay can reach 15%~25% of the initial value, requiring re-tightening to compensate.
[Design gap] No re-tightening step was specified for new equipment within 24~72 hours of operation.
① Set a re-tightening period: schedule the first full re-tightening of new equipment 24~72 hours after startup
② Re-tighten to torque: re-tighten at the original design torque to restore the preload to target
③ Mark and recheck: apply anti-loosening marks before re-tightening and check whether the marks shifted afterwards
④ Priority spots: re-tighten high-stress joints such as anchor bolts, flanges and bearing pedestals first
⑤ Record data: log and compare torques before and after re-tightening to analyze the decay trend
⑥ Second re-tightening: for important equipment, re-tighten a second time after another week of operation
⑦ Decay verification: confirm the preload has recovered from the increase in re-tightening torque
⑧ Standardize process: write break-in re-tightening into the equipment commissioning procedure
GB/T 3098.1-2010 Mechanical properties of fasteners - Bolts, screws and studs