E46-446 · Commissioning & Run-In · Complete equipment set · ★★
The equipment skipped the no-load stage and was trial-run directly under load; a hidden alignment problem was exposed under load and the coupling broke.
[Mechanism] Without staged exposure, hidden defects are amplified into damage under full load.
[Calculation] Loading directly applies stress in one step, so the weakest link breaks first.
[Design gap] No no-load, half-load and full-load stages were defined.
① Stage it: no load first, then half load, then full load, holding each for a set time
② Check each stage: check vibration, temperature and abnormal noise at every stage
③ Gate: move to the next stage only when this stage's data is acceptable
④ Loading: increase the load in steps and continue only after it stabilizes
⑤ Record: record each stage's data as a trend
⑥ Stop rule: on any abnormality, return to the previous stage to investigate
⑦ Quality verification: confirm acceptance by the data of every stage, confirmed by data
⑧ Standardize process: write staged trial running into the trial-run plan, controlling at the source
GB/T 50231-2009 General code for construction and acceptance of mechanical equipment installation engineering