E41-180 · Screw Selection · Large Floor-Type Boring and Milling Machine Screw Foundation · ★★★★★
After the floor-type boring and milling machine had been installed and running for half a year, the X-axis guideway levelness degraded from 0.02mm/m to 0.12mm/m, and the screw-to-guideway parallelism went out of tolerance. The machine's entire foundation settled unevenly.
The equipment foundation was 200mm-thick concrete (C20) with no ground reinforcement. The equipment weighed 35 tons total, and the ground bearing capacity was insufficient (actual 80kPa, required ≥120kPa). Under the equipment's own weight and cutting vibration, the foundation settled unevenly. Settlement was about 8mm in the first 3 months (primary settlement phase) and about 3mm from month 3 to 6 (creep phase). One side settled 5mm more than the other, tilting the guideway. As the screw tilted with the guideway it saw an extra radial load against the nut, accelerating wear. Meanwhile foundation deformation shifted the relative positions of the two screw bearing housings, inducing bending stress in the screw.
① Heavy-equipment foundation requirements: concrete thickness ≥300mm (C25 or above) with a double-layer rebar mesh\n② Ground bearing capacity ≥120kPa (soft-soil sites need pile reinforcement)\n③ Foundation curing period ≥28 days after construction (for complete cement hydration)\n④ Continuously monitor foundation settlement after installation (once per quarter, for 2 years)\n⑤ Embed adjustable leveling pads (M24 adjusting bolts, allowing leveling within ±5mm)
FT_11 Ball Screw Selection