E41-467 · Other Selection · Foundation Bolt Grout Not Compact · ★★★★
When tightening the compressor foundation bolts (M30×800 mm), the bolts were pulled out about 10 mm; there was a gap between the grout (non-shrink grout) and the foundation hole wall.
The foundation-bolt hole (Φ80 mm, 600 mm deep) was not cleaned before grouting (about 50 ml water remained). After pouring non-shrink grout, the water mixed with it (water-cement ratio rose from 0.4 to about 0.6) and grout strength dropped from C35 to about C20. The trapped water also formed a water pocket (about 50 ml) at the hole bottom, and bubbles/voids formed between grout and hole wall (void ratio about 10%). After 7 days curing, the bolt was tightened to 800 Nm (M30, preload about 250 kN). Under this preload the bond surface (effective bond area about 70%) carried shear stress τ = F/A = 250000/(0.7×π×0.04×0.6) ≈ 4.7 MPa, exceeding the grout-to-concrete bond strength (about 2–3 MPa), so the bolt pulled out about 10 mm.
① Clean the foundation-bolt hole before grouting (blow out with compressed air and pump out standing water).\n② Roughen the hole wall (increase bond strength).\n③ Strictly control the grout mix ratio (water-cement ratio ≤ 0.4).\n④ After grouting, cure ≥3 days (strength ≥30 MPa) before tightening bolts.\n⑤ Apply bolt tightening torque in 3 stages (50% → 75% → 100%), 30 min apart.
FT_Machine Design Handbook