Knowledge Base › Structural Design Error Case Study › Wind Turbine Tower Foundation Ring Settlement Differential

Wind Turbine Tower Foundation Ring Settlement Differential

E42-360 · Insufficient Stiffness · 2MW Wind Turbine Tower Foundation Ring · ★★★

Problem Description

The 2MW wind turbine tower foundation ring (Φ4200) has a differential settlement of 18mm on both sides, exceeding the 5mm allowance; the tower tilts and vibrates heavily, with 2 monthly inspections

Root Cause

[Settlement Differential] The pile cap under the foundation ring has uneven stiffness, with a settlement differential of 18mm.
[Tilt] The tower deviates from vertical, causing aerodynamic imbalance.
[Design Omission] The pile cap was not analyzed by FEA and not leveled; safety factor 1.3.

Corrective Solution

1) Thicken the pile cap and densify reinforcement;
2) Add a leveling cushion under the foundation ring;
3) FEA settlement verification;
4) Install laser inclinometer;
5) Measure settlement differential at each foundation;
6) Dense grouting;
7) Limit operating wind speed;
8) Periodic monitoring.

Checklist

Reference

GB/T 18451.1-2012