Wind-Tower Flange Bolt Wind-Vibration Loosening Causing Tower Deflection

E42-401 · Threaded Fastener Loosening · WTG 2.0MW Wind Turbine Tower · ★★★

Problem Description

WTG 2.0MW wind turbine tower (80m high) bottom-section flange M36 bolts loosen; tower-top deflection 28mm exceeds the 15 allowance; 2 inspections per month

Root Cause

[Preload Decay] Flange bolts designed preload 380kN; wind-vibration lateral alternation decays torque 35% to 247kN. [Loosening] Friction locking fails and bolts turn loose. [Design Omission] Locking not checked against wind-load spectrum, no hydraulic tensioning; safety factor 1.2 (should be ≥1.5).

Corrective Solution

1) Switch bolts to hydraulic tensioning preload to 420kN;
2) Add disc-spring lock washers;
3) Control flange-face flatness ≤0.1mm;
4) Spot-weld nuts against rotation;
5) Quarterly torque sampling;
6) Add vibration monitoring alarm;
7) Limit operating wind speed;
8) Mandatory replacement at end of life.

Checklist

Reference

GB/T 31708-2015