Knowledge Base › Tolerance and Fit Error Case › Engine Block Multi-Process Hole-Spacing Accumulation

Engine Block Multi-Process Hole-Spacing Accumulation

E43-457 · Dimensional-Chain Accumulation · Cylinder bore spacing designed 100±0.02, measured 100.09 after 5 set-ups · ★★★

Problem Description

Multi-process hole-spacing accumulation on the block reached 0.09mm out of tolerance, causing piston sticking.

Root Cause

[Mechanism] Datum transfer across multiple processes accumulated, so the closed loop (hole spacing) went out of tolerance.
[Calculation] T0=√(5×0.04²)=0.09, 4.5× the 0.02 allowance.
[Design Omission] Non-unified datum accumulated; design defect → hole spacing out of tolerance.

Corrective Solution

1) Unify the datum and machine in one set-up;
2) Allocate process tolerance per T0;
3) Unify the datum;
4) Coordinate boring control;
5) Selective matching by measurement;
6) Leave grinding stock;
7) CMM hole-spacing check;
8) First-article hole spacing measured ≤0.02.

Checklist

Reference

GB/T 5847-2004 Dimensional chain — Calculation method