E44-395 · Water Hammer and Pressure Surge · Isolation Valve Internal Leakage · ★★
Internal leakage through the isolation valve lets residual pressure in the pipe build up; on pump start, pressure stacks to Δp=1.3MPa exceeding the allowable, blowing out gaskets.
[Internal Leakage] Valve leakage lets residual pressure build up, stacking the wave on start-up.
[Leakage] Δp=1.3 exceeds the allowable and leaks.
[Design Omission] Internal leakage was not repaired and pressure was not relieved — leakage caused the hammer.
1) Repair isolation-valve internal leakage to restore true shutoff: leakage let residual pressure build and stack Δp=1.3 on start, exceeding and leaking; repair restores true shutoff;
2) Relieve pressure before start-up: residual pressure stacks, so it is vented first;
3) Check stacked pressure ≤ allowable: stacking exceeded the limit, so it is calculated;
4) Install a surge arrester to cut the peak, because the amplitude exceeds the limit; hence peak absorption;
5) Up-rate the pipe or use a metal gasket: a low allowable caused leakage, so the rating is raised;
6) Periodically test valve tightness: leakage progresses gradually, so tightness is tested;
7) Recheck by water-hammer simulation, because estimates fall short; hence simulation;
8) Write internal-leakage repair into the procedure: the original omission was the root cause of the hammer, so procedure review enforces it.
GB/T 32284-2015 Code for design of pump stations - Water hammer protection