MOULDLKnowledge Base3D Model DownloadsMembership
中文版Model Store »
HomeModels
Table of contents

Knowledge Base Home

📐 Standard Data

🧮 Calculators

📖 Selection Guides

🏭 Material Grades

❓ Engineer FAQ

🗂 Quick-Reference Categories

❌ Error Case Studies

📚 Technical Articles

Knowledge Base › Fluid Systems Error Case › Riser-Top Air Lock

Riser-Top Air Lock

E44-069 · Two-Phase Flow and Gas Binding · Vertical Riser · ★★

Problem Description

Gas collected at the top of the riser and formed an air lock; the flow fluctuated by ±40%, and downstream water supply was unstable.

Root Cause

[Air Lock] Gas at the riser top blocks the liquid column and forms an air lock, changing the flow cross-section.
[Calculation] The air lock reduced the effective cross-section by 40%, matching the flow fluctuation.
[Design Omission] No top vent was provided and flow direction was not controlled; the air lock made flow unstable.

Corrective Solution

1) Provide an automatic vent valve at the pipe top; air locks form at the riser top, and an automatic valve vents continuously, eliminating the lock and restoring the flow section;
2) Slope the pipe top toward the vent; the slope carries gas to the vent point instead of letting it linger, preventing air-lock formation;
3) Control flow velocity to avoid entrained gas (maintain stable full-pipe flow); too low a velocity lets gas stratify and be carried along, so controlled velocity stabilizes flow and reduces air locks;
4) Monitor flow fluctuation (should be ≤±5%); a ±40% swing directly indicates an air lock, and monitoring quantifies it for early alarm;
5) Provide a surge-relief tank to smooth the fluctuation; the gas cushion in the tank buffers instant swings and stabilizes downstream supply, damping the ±40% fluctuation;
6) Periodically vent the top gas; air locks can regenerate, so periodic venting prevents accumulation and keeps flow stable;
7) On commissioning, verify stable flow (fluctuation ≤5%); stable flow is the goal and must be measured, giving acceptance;
8) Include venting in the piping layout specification; the original lack of top venting caused the air lock, so vent points are laid out at the layout stage.

Checklist

Reference

GB/T 20801-2020 Pressure piping code

Related model download:Understood the principle and ready to try?Go to MOULDL to download related 3D models and CAD drawings for free »
MOULDL · Mechanical Engineering Knowledge Base · free self-study reference for machine designers, 3D CAD models at MOULDL