E44-423 · Two-Phase Flow and Gas Binding · Cooler Shell-Side Gas Buildup · ★★
Gas buildup on the shell side cuts the effective heat-transfer area by 30%, the outlet temperature rises 8℃, and cooling becomes insufficient.
[Mechanism] Shell-side gas occupies area and cuts effective heat transfer by 30%.
[Calculation] The outlet rises 8℃ and cooling becomes insufficient.
[Design Omission] No shell-side venting and no high-point vents were provided — the cause of the gas-reduced heat transfer.
1) Fit vent valves at the shell-side high points for continuous venting; gas buildup cuts effective area 30%, raises 8℃ and leaves cooling short, so vent to keep the area;
2) Slope the tube layout toward the vents; a flat arrangement accumulates gas, so slope it;
3) Install a gas header tank for centralized venting; scattered vents are hard to drain, so collect the gas;
4) Check the effective heat-transfer area; gas occupies and loses area, so verify it;
5) Monitor the outlet temperature to catch the rise early; it climbs gradually, so watch the temperature;
6) Vent periodically; buildup is gradual, so vent and inspect;
7) Control the feed gas content; more gas takes up area, so limit it;
8) Write shell-side venting into the design; the original gas buildup was the root cause of the reduced transfer, so gate it at design stage.
GB/T 5657-2013 Technical specifications for centrifugal pumps