E44-440 · Two-Phase Flow and Gas Binding · Long Horizontal Pipe Stratification · ★★
Gas-liquid stratification in a long horizontal line leaves gas-binding at the top and liquid pooled at the bottom, dropping the end flow 25%.
[Mechanism] In a long horizontal line the gas rises and the liquid settles, stratifying the flow.
[Calculation] The gas layer on top binds the flow and drops it 25%.
[Design Omission] No slope and no venting were provided — the cause of the long-line stratification.
1) Slope the line and vent it in sections; a long horizontal line stratifies, the top gas binds the flow and drops it 25%, so slope and vent to break the layer;
2) Keep a slope ≥0.003 so gas rises; a flat line stratifies, so slope the layout;
3) Install a gas header tank for centralized venting; gas collects at the top, so collect it;
4) Count the stratification loss into the total resistance; gas binding causes loss, so account for it fully;
5) Monitor the end flow to catch the drop early; stratification builds gradually, so watch the flow;
6) Keep air out of the pump suction; gas causes damage, so prevent it;
7) Vent periodically; stratification builds gradually, so vent and inspect;
8) Write the slope into the layout; the original stratification was the root cause of binding, so gate it at layout stage.
GB/T 5657-2013 Technical specifications for centrifugal pumps