Knowledge Base › Fluid Systems Error Case › Air Preheater Low-Temperature Corrosion Plugging

Air Preheater Low-Temperature Corrosion Plugging

E44-513 · Heat Exchanger Fouling and Insufficient Heat Transfer · Regenerative Air Preheater · ★★

Problem Description

Low-temp dewpoint corrosion plugging, air leakage, heat-transfer loss

Root Cause

[Mechanism] Wall temperature < acid dewpoint; acid corrodes and plugs the holes.
[Calculation] Wall temperature <120℃ causes acid condensation, raises corrosion rate, plugs holes and leaks air.
[Design Omission] No wall-temperature control and no air heating, so corrosion plugs the unit.

Corrective Solution

1) Use an air preheater to raise wall temperature > acid dewpoint (≥120℃); when wall temp falls below the dewpoint, sulfuric acid condenses, raising corrosion rate and plugging holes with leakage, so raising temperature prevents condensation and corrosion;
2) Control flue-gas temperature to avoid lows (> dewpoint +10℃); low exhaust temperature causes acid condensation, so temperature control prevents it;
3) Coat heat-transfer surfaces with acid-resistant enamel; sulfuric acid corrodes the holes, and the enamel barrier extends life;
4) Monitor air-leakage rate online (alarm >8%); corrosion breakthrough causes leakage and efficiency loss, so early detection allows sealing;
5) Schedule sootblowing to prevent ash-driven corrosion; damp ash worsens acid corrosion and plugs passages, so blowing keeps surfaces clean;
6) Control fuel sulfur (low-sulfur / desulfurization); sulfur burns to SO3 and forms acid, so controlling sulfur cuts acid;
7) Inspect plugged holes on schedule (borescope each quarter); corrosion enlarges holes and leaks air, so inspection guides plugging;
8) Write air heating and wall-temperature control into the air-preheater procedure; the original design omitted air heating and wall-temperature control, the root cause of corrosion, so the procedure closes the loop.

Checklist

Reference

GB/T 151-2014 Heat exchangers