Chilled-Water Heat Exchanger Biological Slime

E44-529 · Heat Exchanger Fouling and Insufficient Heat Exchange · Copper Chilled-Water Heat Exchanger · ★★

Problem Description

Slime adhesion, reduced K, poor refrigeration, higher energy consumption

Root Cause

[Mechanism] Bacteria and algae form slime that adheres to the wall.
[Calculation] Slime fouling factor Rf=0.3 lowers K by 30%, reduces refrigeration capacity Q, and raises energy consumption.
[Design Omission] No biocide treatment and no flushing, so slime accumulated.

Corrective Solution

1) Add biocide and algaecide treatment and flush to keep Rf<0.1; because microbial slime on the wall with Rf=0.3 lowers K by 30%, cuts refrigeration Q and raises energy use, treatment plus flushing restores K;
2) Schedule backwashing (periodic reverse flush); because slime adheres and hardens over time, backwashing removes it;
3) Add online K monitoring (alarm on a 10% K drop); because slime lowers K as the first visible symptom, K monitoring gives early warning;
4) Keep the chilled-water side clean (closed loop / corrosion-inhibited); because dirty water grows bacteria and algae into slime, cleanliness suppresses growth;
5) Raise flow velocity to prevent settling (≥1.2m/s); because low flow lets microbes settle and adhere, higher velocity suppresses slime;
6) Add side-stream filtration to reduce biomass; because more biomass means more adhesion, side-stream filtration cuts the load;
7) Inspect slime thickness on schedule (thickness measurement / visual); because slime thickens gradually and lowers K, thickness checks guide treatment timing;
8) Write biocide treatment and backwashing into the chilled-water procedure; because the original design omitted biocide and flushing, the root cause of slime, the procedure closes the loop.

Checklist

Reference

GB/T 151-2014 Heat exchangers