Branch Pipe Diameter Mismatch Causing Flow Deviation

E44-727 · Uneven Flow Distribution · Branch pipe · ★★

Problem Description

Diameter difference, resistance variation

Root Cause

[Mechanism] A diameter difference deviates the flow.
[Calculation] The diameter difference makes the resistances differ and deviates the flow.
[Design Omission] No standardization of the diameters, no verification, and no inspection were provided, so the diameters differ.

Corrective Solution

1) Standardize the branch pipe diameter (same diameter on each branch, deviation ≤3%), because the original diameter difference made the branch resistances differ by >15% and deviated the flow, thereby standardizing the diameters and evening the resistances;
2) Verify the resistance of each branch (calculate along the line, difference ≤5%), because a difference causes deviation and verification evens it, thereby verifying the resistances;
3) Provide a balancing valve for adjustment (each branch, adjust to even), because a deviation makes the flows vary and adjustment evens them, thereby balancing;
4) Check the diameter difference (measure each branch, correct above a 5% difference), because a gradual difference is invisible and checking catches it, thereby giving early warning;
5) Limit the velocity against deviation (each branch ≤2.5m/s), because an excessive velocity causes deviation and limiting slows it, thereby limiting the velocity;
6) Perform a hydraulic check (flow of each branch, readjust above a 5% deviation), because the lack of calculation caused the deviation and calculation verifies it, thereby performing the hydraulic check;
7) Check the flow distribution at fixed intervals (meter and record each branch), because gradual deviation is invisible and checking reveals it, thereby providing data;
8) Write the diameter standardization and resistance verification into the calculation sheet (resistance table for each branch), because the missing standardization was the root cause of the diameter difference and freezing it into the calculation sheet enforces control.

Checklist

Reference

GB/T 20801.3-2020 Design code for industrial metallic piping