Large Deviation Between Weighing and Float Gauge

E44-185 · Level Control Failure · Tank Weighing + Float Gauge · ★★

Problem Description

The weighing module and the float gauge differ by 1.2t, so the true level cannot be determined

Root Cause

[Source of Deviation] The weighing is disturbed by foundation settlement and the float gauge by adhesion.
[Large Discrepancy] The errors of the two sources stack up.
[Design Omission] No cross-checking and no periodic calibration were provided, so the readings disagree.

Corrective Solution

1) Cross-check and calibrate the weighing and the float gauge at intervals, because a 1.2t difference makes the true value hard to determine and cross-checking establishes it, thereby determining the truth;
2) Consolidate and level the weighing-module foundation against settlement, because settlement causes the deviation and consolidation prevents it, thereby preventing settlement;
3) Clean adhesion off the float gauge to prevent deviation, because adhesion causes the deviation and cleaning removes it, thereby clearing the adhesion;
4) Designate a primary meter as the single data source, because the two sources differ and one source unifies them, thereby unifying the data;
5) Keep calibration records traceable, because analysis needs them and records provide this, thereby documenting the work;
6) Apply temperature compensation to the weighing, because thermal expansion changes the weight and compensation corrects it, thereby compensating for temperature;
7) Prove on trial run that the deviation between the two meters is ≤ the allowance, because the design requires measurement and the trial run confirms it, thereby confirming delivery;
8) Include cross-checking in level management, because the omitted cross-check was the root cause of the large deviation and management must include it.

Checklist

Reference

GB/T 20819-2018 Process control — System evaluation