Water Seal Failure in a Siphon Pipe

E44-913 · Siphon and Backflow · Siphon Pipe · ★★

Problem Description

Water seal failure, backflow, contamination

Root Cause

[Mechanism] The U-shaped water seal is too short or is drawn empty by the siphon, losing the liquid seal and letting gas or medium from downstream surge back.
[Calculation] A water seal height h=0.3 m resists only 0.003 MPa and is breached by a backflow positive pressure of 0.01 MPa; safety requires h≥1.0 m to resist 0.01 MPa.
[Design Omission] Insufficient water seal height, no makeup water, and no pressure-resistance check.

Corrective Solution

1) Raise the water seal height to ≥1.0 m (the original 0.3 m was insufficient), because the seal withstands pressure = ρgh and 1.0 m resists 0.01 MPa > the backflow positive pressure, thereby keeping the seal from being breached;
2) Provide an overflow makeup-water pipe to the water seal (always full, never drawn empty), because the siphon draws it empty and loses the seal while makeup water keeps it full, thereby keeping the seal in place;
3) Add a check valve ahead of the water seal to block backflow positive pressure, because positive pressure is the breaching source and the check valve cuts it, thereby protecting the seal;
4) Provide a breather at the seal top to prevent dry-out (break the vacuum to keep the seal), because negative pressure draws the seal and the breather breaks the vacuum to hold the level, thereby keeping the seal from being drained dry;
5) Perform a water-seal pressure test (apply pressure and verify it is not breached), because the design omitted the height check and the test confirms the pressure resistance, thereby determining the seal height from data;
6) Provide a seal level gauge with a low alarm (<0.8 m), because the seal drops before it fails and allows early makeup, thereby monitoring the seal to prevent failure;
7) Provide pressure relief on the backflow side (relieve on overpressure), because overpressure breaches the seal while relief lowers the positive pressure, thereby protecting the seal;
8) Write the water seal height and makeup water into the installation card, because the root cause of failure is a low seal that is drawn empty, so installation must govern to prevent surging.

Checklist

Reference

GB/T 20801.3-2020 Design code for industrial metallic piping