Backflow Flooding the Trench

E44-946 · Siphon and Backflow · Trench · ★★★

Problem Description

Backflow, trench flooding, damage

Root Cause

[Mechanism] The trench elevation is lower than the upstream liquid level, so backflow floods the trench and damages the equipment and the environment.
[Calculation] With an inside-outside difference of 1.6 m, the backflow Q≈0.2 m³/s floods the trench 0.12 m deep in 8 min.
[Design Omission] The trench was not raised, not isolated, and had no drainage.

Corrective Solution

1) Raise the trench floor to 0.3 m above the upstream liquid level (originally 1.6 m lower), because a positive elevation difference eliminates backflow into the trench, with a 0.3 m margin, thereby preventing flooding by elevation;
2) Install a slow-closing check valve at the inlet (seepage ≤5 mL/min), because backflow enters the trench through the inlet and the check valve cuts off the source, thereby isolating it;
3) Provide a sump pit and a drainage pump (40 m³/h) in the trench, because slight seepage must be drained and the pit collects while the pump discharges, thereby providing double insurance;
4) Link the inlet liquid level to valve closure (close on flooding), because flooding first shows as a liquid level and the linkage cuts off immediately, thereby monitoring for a fast shutoff;
5) Perform a backflow test (open the inlet and verify the trench is not flooded), because the design omitted the height check and the test confirms the elevation, thereby determining the raise from data;
6) Provide a liquid level alarm (>0.1 m), because flooding precedes damage and early warning helps, thereby monitoring the level to prevent damage;
7) In the pump shutdown sequence, close the inlet before stopping (interlock), because a wrong sequence causes flooding and sequence control suppresses it, thereby controlling the shutdown to prevent flooding;
8) Write the trench elevation and check valve into the regulations, because the root cause of flooding is the low elevation without isolation, so the regulations must govern to prevent flooding.

Checklist

Reference

GB/T 20801.3-2020 Design code for industrial metallic piping