E46-110 · Assembly Sequence & Datum · Machine Final Assembly · ★★
The external piping was installed before the internal components of the frame; the piping blocked the access, the internal bolts could not be tightened and the piping had to be removed for rework.
[Mechanism] The assembly tree order of inside out and bottom up was not followed; working outside in caused interference.
[Calculation] The interference makes the internal parts unreachable and doubles the assembly labor.
[Design gap] No layered assembly sequence was drawn up.
① Follow the assembly tree: work in the assembly tree order of inside before outside, bottom before top and heavy before light
② Core first: install and fasten the core components inside the frame first, then the external piping and covers
③ Accessibility: before assembly confirm every bolt and connection has working space and is not blocked
④ Staged testing: after completing each layer carry out local testing to detect interference early
⑤ Prevent wrong installation: check part numbers and positions against the assembly drawing to prevent mismatching
⑥ In-process inspection: after each assembly layer check accessibility and fastening and correct deviations early
⑦ Quality verification: confirm there is no interference by a functional trial run after final assembly
⑧ Standardize process: write the assembly tree sequence into the assembly process card, controlling at the source
JB/T 5000.10-2007 General technical conditions for heavy machinery - Part 10: Assembly