E46-412 · Commissioning & Run-In · Vertical multistage pump · ★★
The vertical pump was run after installation without measuring the rotor runout; the rotating parts rubbed against the guide bearing, the guide bearing burned out and the pump stopped lifting water.
[Mechanism] A bent rotor or offset center makes the runout exceed the clearance, and rotation scrapes the guide bearing.
[Calculation] When the runout exceeds 0.15mm it interferes with the guide-bearing clearance, causing dry friction and heat.
[Design gap] No barring-over runout measurement or runout correction was done.
① Bar over and measure: bar the rotor over by hand and measure the runout with a dial gauge; correct it first if it exceeds 0.10mm
② Correct runout: measure the coupling and shaft-end runout; straighten or shim if out of tolerance
③ Verify clearance: confirm the clearance between the rotating and stationary parts is greater than the runout
④ Watch slow rotation: jog slowly and listen for scraping
⑤ Check the guide bearing: before assembly check the guide-bearing bore fit with the shaft to prevent tightness
⑥ Record all: record the runout and dial-gauge values, keeping a baseline
⑦ Quality verification: confirm acceptance by runout and absence of scraping noise, confirmed by data
⑧ Standardize process: write the barring-over runout measurement into the installation card, controlling at the source
GB/T 5657-2013 Technical specifications for centrifugal pumps