E46-413 · Commissioning & Run-In · Pneumatic actuator · ★★
The pneumatic system was commissioned in a humid environment without draining the condensate; in winter the water trapped in the valves froze, making the cylinders sluggish or even stuck.
[Mechanism] Condensate in the compressed air freezes in the low-temperature section and blocks the air line.
[Calculation] When the dew point is 10℃ above the ambient temperature, water condenses out and freezes at low temperature.
[Design gap] No automatic drain was provided, nor was periodic blowdown done.
① Install drains: fit automatic drains at the air receiver and low points to discharge on a timer
② Blowdown at commissioning: manually drain all condensate from the piping before admitting air
③ Dry: add a refrigerated dryer to bring the dew point below ambient
④ Drain at low points: open the low-point drain valve before start-up to release trapped water
⑤ Watch the motion: check whether the cylinder strokes smoothly and investigate any sluggishness for blockage
⑥ Insulate: insulate the piping in the low-temperature section to prevent freezing
⑦ Quality verification: confirm acceptance by the drain records and smooth motion, confirmed by data
⑧ Standardize process: write the blowdown steps into the pneumatic commissioning sheet, controlling at the source
GB/T 7932-2017 General technical conditions for pneumatic systems