E46-417 · Commissioning & Run-In · Newly installed unit · ★★
No operating data was recorded during the equipment's run-in; after going into service the vibration crept up but with no baseline to compare against, it was impossible to tell whether it was normal.
[Mechanism] Without an initial baseline the degradation trend cannot be judged, so early action is missed.
[Calculation] Without a baseline the out-of-tolerance thresholds cannot be set and hidden faults accumulate.
[Design gap] No run-in data file was established.
① Build a baseline: record vibration, temperature, pressure and current in full during run-in
② Sample on schedule: sample at fixed intervals at each stage to form a trend line
③ Set thresholds: set alarm limits from the baseline and warn as soon as they are exceeded
④ Archive: file the data for operations to compare against
⑤ Train: make the operating staff aware of the baseline values and able to spot anomalies
⑥ Retest: retest a month into service to see the drift
⑦ Quality verification: confirm traceability by complete baseline data, confirmed by data
⑧ Standardize process: write data filing into the commissioning handover, controlling at the source
GB/T 6075.1-2012 Mechanical vibration - Measurement and evaluation of machine vibration on non-rotating parts