E46-416 · Commissioning & Run-In · Complete equipment set · ★★★
The control cabinet was energized before the mechanical checks; a motor miswired with the wrong phase sequence ran in reverse and a loose coupling bolt was thrown out and injured someone.
[Mechanism] Energizing without a prior mechanical safety check lets hidden hazards surface as accidents while live.
[Calculation] The reverse-running centrifugal force pulls the untightened bolt beyond yield and throws it out.
[Design gap] The mechanical-before-electrical commissioning sequence was not followed.
① Mechanical before electrical: complete the mechanical check and tightening before energizing the control circuit
② Retighten couplings: retighten all coupling and connecting bolts before energizing
③ Check guards: confirm the guards and emergency stops are in place before energizing
④ Jog: jog electrically first to confirm the rotation direction and motion
⑤ Isolate: post warnings around the commissioning area and keep non-commissioning staff away
⑥ Record: record the pre-energization checks and sign off
⑦ Quality verification: confirm safety by the mechanical checklist, confirmed by data
⑧ Standardize process: write the commissioning sequence into the safe work instruction, controlling at the source
GB/T 5226.1-2019 Electrical safety of machinery - Electrical equipment of machines - Part 1