E46-423 · Commissioning & Run-In · Hydraulic piston pump · ★★★
At first start-up the piston pump was run without filling the housing with oil; within minutes the valve plate and cylinder block ground dry and seized, and the pump failed.
[Mechanism] With no oil film established before start-up, the metal surfaces rub dry and seize at high temperature in an instant.
[Calculation] Without an oil film the friction coefficient exceeds 0.3 and the temperature rise rate exceeds 100℃ per minute.
[Design gap] The fill-and-vent start-up procedure was not followed.
① Fill first: before starting, fill the pump housing and suction line with oil and expel the air
② Jog: jog for a few seconds so that oil reaches all friction pairs before continuous running
③ Low-pressure circulation: run at low pressure for a few minutes to build the oil film
④ Check suction: check the suction line for air leaks to prevent cavitation
⑤ Measure temperature: listen for abnormal noise and measure the housing temperature, stopping if it overheats
⑥ Oil cleanliness: confirm that the oil cleanliness meets the requirement to prevent particle scratching
⑦ Quality verification: confirm acceptance by absence of abnormal noise and normal temperature rise, confirmed by data
⑧ Standardize process: write the oil-fill procedure into pump commissioning, controlling at the source
GB/T 3766-2015 General technical conditions for hydraulic systems