E46-427 · Commissioning & Run-In · Water-cooling jacket · ★★
The water-cooling system was filled without venting the air; an air lock formed at the high point, the local water temperature exceeded the boiling point and vaporized, and cavitation perforated the pipe wall and caused leakage.
[Mechanism] The air lock blocks the water flow, leaving a locally uncooled region where the temperature soars and vaporizes.
[Calculation] In the air-locked section the flow velocity is near zero and the wall temperature exceeds 100℃, vaporizing the water and causing erosion.
[Design gap] The high-point vent valve was not opened while filling.
① Vent high points: open the high-point vent valve while filling until a continuous water stream comes out
② Fill slowly: fill at low flow to drive out the air and prevent air entrapment
③ Bypass: flow through the bypass to fill the piping before switching to the main circuit
④ Temperature rounds: during operation patrol the high-point wall temperature and vent at once if it is abnormal
⑤ Flow check: check the flow in each branch; a missing flow means trapped air
⑥ Record: record the venting and filling process
⑦ Quality verification: confirm acceptance by no air lock and even temperature, confirmed by data
⑧ Standardize process: write filling and venting into the commissioning sheet, controlling at the source
GB/T 9222-2008 Strength calculation of pressure parts for water-tube boilers