E46-435 · Commissioning & Run-In · Vacuum unit · ★★
The main vacuum pump was started before evacuation; running at atmospheric pressure made the pump oil heat up quickly and oxidize internally, and the pumping speed dropped.
[Mechanism] Running at atmospheric pressure departs from the design condition, and friction and temperature rise increase sharply.
[Calculation] At atmospheric pressure the power demand is several times the rated value, and the temperature rise runs away.
[Design gap] The sequence of rough pumping first and then the main pump was not followed.
① Rough-pump first: use the backing pump to reach the specified pressure before starting the main pump
② Sequence control: interlock the main pump so that it starts only when the pressure reaches the target
③ Measure temperature: monitor the oil temperature in operation and stop if it exceeds the limit
④ Check for leaks: if the pumping speed is below target, check the joints for air leaks
⑤ Check oil: inspect the pump oil color and replace it if oxidized
⑥ Record: record the evacuation curve
⑦ Quality verification: confirm acceptance by ultimate pressure and temperature rise, confirmed by data
⑧ Standardize process: write the evacuation sequence into the start-up card, controlling at the source
GB/T 19955.1-2005 Vacuum technology - Turbomolecular pumps - Measurement of performance characteristics