E46-434 · Commissioning & Run-In · Vertical bearing housing · ★★
The bearing housing base plate was only tack-welded without secondary grouting; operating vibration shifted the housing, the shaft centerline deviated and vibration increased.
[Mechanism] Weak fixing lets the housing creep under alternating forces, accumulating offset.
[Calculation] Without grouting the base has weak shear resistance, and a displacement over 0.2mm causes misalignment.
[Design gap] No foundation grouting or curing was done.
① Secondary grout: fill the space between the housing base and the foundation with secondary grout
② Cure: cure the grout to the required standard before tightening the anchor bolts
③ Level: level the housing with shims before grouting
④ Tighten anchors: tighten the anchor bolts to torque in several passes
⑤ Re-center: re-measure alignment after grouting to prevent offset
⑥ Record: record the grouting and the tightening forces
⑦ Quality verification: confirm acceptance by alignment and absence of looseness, confirmed by data
⑧ Standardize process: write the grouting procedure into the installation specification, controlling at the source
GB/T 50231-2009 General code for construction and acceptance of mechanical equipment installation engineering