E46-437 · Commissioning & Run-In · Machine train commissioning · ★★
The temporary shims and jacks added for alignment during commissioning were not removed before running, so the rotating parts jammed and the motor overloaded.
[Mechanism] The left-behind items intrude into the running clearance, obstructing rotation and causing stall.
[Calculation] The left-behind items raise the rotational resistance beyond the starting torque, and the current spikes.
[Design gap] No clearance recheck was done once commissioning was finished.
① Clearance list: list the commissioning tooling and dismantle each item as soon as it is finished
② Recheck: a designated person rechecks the motion area for foreign objects before start-up
③ Bar over: bar the shaft over by hand to confirm there is no binding before energizing
④ Jog: jog the unit and check that rotation is smooth and unobstructed
⑤ Current: measure the starting current and stop to investigate if it is abnormal
⑥ Record: record the clearance work and who performed the recheck
⑦ Quality verification: confirm there are no foreign objects by smooth barring over, confirmed by data
⑧ Standardize process: write the clearance recheck into the handover inspection, controlling at the source
GB/T 50231-2009 General code for construction and acceptance of mechanical equipment installation engineering