E46-448 · Commissioning & Run-In · Centrifugal pump · ★★★
The centrifugal pump was started without priming; the impeller ran dry with no liquid, and the mechanical seal burned out from dry friction and leaked.
[Mechanism] With no liquid the mechanical seal has neither lubrication nor cooling, and dry friction damages it at high temperature in an instant.
[Calculation] A few minutes of dry running pushes the seal temperature above 200℃ and it carbonizes and fails.
[Design gap] Start-up with pump priming and venting was not carried out.
① Prime first: fill the pump casing through the priming port and expel the air before starting
② Vent: open the casing vent valve until the outflow carries no bubbles
③ Jog: jog to check the rotation direction and outflow, and continue only if normal
④ Seal check: during operation check the mechanical seal for leakage or overheating
⑤ Flow check: check the discharge flow; if there is none, the air has not been fully expelled
⑥ Record: record the priming and venting
⑦ Quality verification: confirm acceptance by the outflow and an intact mechanical seal, confirmed by data
⑧ Standardize process: write the priming procedure into the pump start-up card, controlling at the source
GB/T 5657-2013 Technical specifications for centrifugal pumps